ALERTS

Stay tuned here to the latest alerts from your water system.  Subscribe and receive all published alerts delivered via email and text straight to your inbox.  Just another way we are working to better serve our community.

Kemp Lake Water Source Replacement Project

Anticipated Completion Date: Oct 31, 2019
We now have our contractors available again and work begins this week on constructing the pump house. We are still waiting for some of the parts to arrive to complete the plumbing work. Unfortunately the supplier is unable to give us a delivery date. Once the work is completed, we can request final inspection, connection and meter installation by the CRD Integrated Water department. Until that time we won't know what their schedule is like.